Updates

Important Update: Extended working hours to increase height of tower crane

We would like to take the opportunity to give you advance warning that the New Regent’s College project has been granted permission by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 16th June 8am - 8pm Sunday 17th June 9am - … Continue reading Important Update: Extended working hours to increase height of tower crane

Programme Update: June 2018

During May works to the school have continued with the window frame and glazing in progress to create weather tight internal areas for the school’s fit-out. The school’s internal classroom walls are being built with the new mechanical and electrical services being installed. The pre-cast concrete facade is in progress to the Nile Street block … Continue reading Programme Update: June 2018

Programme Update: May 2018

During May, the tower’s concrete façade and internal works will continue to progress. The school’s internal fit-out works and window installation will continue. The Nile Street Block’s concrete cladding panels will continue to be installed on the building, along with the installation of steel column and beams on the front of the building. Community Engagement … Continue reading Programme Update: May 2018

Programme Update: April 2018

During March, installation of the pre-cast concrete panels to the school has continued to progress well, helping to protect the inside of the building from bad weather. Progress to the tower is continuing with the lift core now built up to level 19, and the slabs following close behind at level 15. Installation of the … Continue reading Programme Update: April 2018

Important Update: Change of date for extended working hours to increase height of tower crane

Due to circumstances outside of the site’s control, the climbing of Tower Crane 1 this coming weekend has been postponed. Permission has been granted by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 14th April 8am - 8pm Sunday 15th April … Continue reading Important Update: Change of date for extended working hours to increase height of tower crane

Important Update: Extended working hours to increase height of tower crane

We would like to take the opportunity to give you advance warning that the New Regent’s College project has been granted permission by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 7th April 8am - 8pm Sunday 8th April 9am - … Continue reading Important Update: Extended working hours to increase height of tower crane

Programme Update: March 2018

During February, the school and tower concrete cladding works have commenced and are progressing well, along with construction of the concrete structure to the tower and the Nile Street block. Basement works are continuing, with construction of the internal blockwork walls nearing completion, whilst the final sections of large heating and cooling plant have been … Continue reading Programme Update: March 2018

Programme Update: February 2018

During January, the structural steelwork for the school’s Sports Hall roof has been installed, and the roof concreted. The concrete works have continued on the tower’s structure, with the lift core now constructed to Level 14 and the floor slabs constructed to Level 10. The concrete works to the Nile Street block have been completed … Continue reading Programme Update: February 2018

Programme Update: January 2018

During December, we have installed the protective screen around the tower to allow the concrete floor slab and column construction to continue up to the 8th floor. The tower’s lift core construction has progressed well and is now at the 12th floor. The concrete walls around the school’s sports hall roof have been constructed to … Continue reading Programme Update: January 2018

Programme Update: December 2017

During November, we have worked hard to complete the new school’s concrete structure. The concrete works to the residential block along Nile Street have now been completed on the second floor. The towers concrete lift core has now been completed to Level 11, whilst the floor slabs have been completed up to Level 6. A … Continue reading Programme Update: December 2017