Updates

Programme Update: April 2018

During March, installation of the pre-cast concrete panels to the school has continued to progress well, helping to protect the inside of the building from bad weather. Progress to the tower is continuing with the lift core now built up to level 19, and the slabs following close behind at level 15. Installation of the … Continue reading Programme Update: April 2018

Important Update: Change of date for extended working hours to increase height of tower crane

Due to circumstances outside of the site’s control, the climbing of Tower Crane 1 this coming weekend has been postponed. Permission has been granted by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 14th April 8am - 8pm Sunday 15th April … Continue reading Important Update: Change of date for extended working hours to increase height of tower crane

Important Update: Extended working hours to increase height of tower crane

We would like to take the opportunity to give you advance warning that the New Regent’s College project has been granted permission by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 7th April 8am - 8pm Sunday 8th April 9am - … Continue reading Important Update: Extended working hours to increase height of tower crane

Programme Update: March 2018

During February, the school and tower concrete cladding works have commenced and are progressing well, along with construction of the concrete structure to the tower and the Nile Street block. Basement works are continuing, with construction of the internal blockwork walls nearing completion, whilst the final sections of large heating and cooling plant have been … Continue reading Programme Update: March 2018

Programme Update: February 2018

During January, the structural steelwork for the school’s Sports Hall roof has been installed, and the roof concreted. The concrete works have continued on the tower’s structure, with the lift core now constructed to Level 14 and the floor slabs constructed to Level 10. The concrete works to the Nile Street block have been completed … Continue reading Programme Update: February 2018

Programme Update: January 2018

During December, we have installed the protective screen around the tower to allow the concrete floor slab and column construction to continue up to the 8th floor. The tower’s lift core construction has progressed well and is now at the 12th floor. The concrete walls around the school’s sports hall roof have been constructed to … Continue reading Programme Update: January 2018

Programme Update: December 2017

During November, we have worked hard to complete the new school’s concrete structure. The concrete works to the residential block along Nile Street have now been completed on the second floor. The towers concrete lift core has now been completed to Level 11, whilst the floor slabs have been completed up to Level 6. A … Continue reading Programme Update: December 2017

Programme Update: November 2017

During October 2017, the project’s ground floor slab has been completed in all areas. The new school’s ground floor columns and walls have been constructed, with the level 1 slab under construction. The residential tower’s core has progressed to level 6, with the level 2 tower slab under construction. The residential block along Nile Street … Continue reading Programme Update: November 2017

Occupational Health Check On Site

As part of our company's wellbeing programme, Clarity Health Care undertook a health screening day at our Nile Street site. A 15 minute consultation that covered height, weight, blood pressure and involved standing on a device that measured BMI, hydration, and muscle mass and biometric age proved to be very popular. Twenty four people took … Continue reading Occupational Health Check On Site

Nile Street site team redecorate Blue Hut Community Hall

As part of our community engagement programme we have undertaken the refurbishment of the Blue Hut with a family run painting and decorating company based in Hackney. The Blue Hut is a community youth centre adjacent to our site that offers services to young people aged between 8 – 25 years old. These services include … Continue reading Nile Street site team redecorate Blue Hut Community Hall