Updates

Programme Update: September 2018

In August, internal works to the school has continued. The tower’s concrete frame works have been completed and removal of the protective screens has commenced. Window and glazing works have commenced on the Nile Street Block, enabling internal works to start on Level 01. During September, the project will swap onto permanent electricity supply. This … Continue reading Programme Update: September 2018

Important Update: Notification of extended working hours for tower crane dismantle

We would like to take the opportunity to give you advance warning that the New Regent’s College project will temporarily extend its working hours on the following dates and times: Saturday 1st September 8am - 8pm Sunday 2nd September 9am - 8pm The reason for the extended opening of the site over the weekend is … Continue reading Important Update: Notification of extended working hours for tower crane dismantle

Programme update: August 2018

In July, works to the school’s internals have continued with the ground slab being screeded ready for the new floor finishes. The tower’s core has been completed and the formwork used to give the concrete is shape has been removed. The concrete floor slabs have reached Level 26. The tower’s cladding installation is progressing well … Continue reading Programme update: August 2018

Programme Update: July 2018

In June the school classrooms have been built and the new mechanical and electrical services have been installed. The glazing is nearly complete, making the building watertight. Cladding is complete to level 12 of the tower, whilst the concrete core is complete to level 27 and the concrete slabs are complete to level 22. The … Continue reading Programme Update: July 2018

Important Update: Extended working hours to increase height of tower crane

We would like to take the opportunity to give you advance warning that the New Regent’s College project has been granted permission by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 16th June 8am - 8pm Sunday 17th June 9am - … Continue reading Important Update: Extended working hours to increase height of tower crane

Programme Update: June 2018

During May works to the school have continued with the window frame and glazing in progress to create weather tight internal areas for the school’s fit-out. The school’s internal classroom walls are being built with the new mechanical and electrical services being installed. The pre-cast concrete facade is in progress to the Nile Street block … Continue reading Programme Update: June 2018

Programme Update: May 2018

During May, the tower’s concrete façade and internal works will continue to progress. The school’s internal fit-out works and window installation will continue. The Nile Street Block’s concrete cladding panels will continue to be installed on the building, along with the installation of steel column and beams on the front of the building. Community Engagement … Continue reading Programme Update: May 2018

Programme Update: April 2018

During March, installation of the pre-cast concrete panels to the school has continued to progress well, helping to protect the inside of the building from bad weather. Progress to the tower is continuing with the lift core now built up to level 19, and the slabs following close behind at level 15. Installation of the … Continue reading Programme Update: April 2018

Important Update: Change of date for extended working hours to increase height of tower crane

Due to circumstances outside of the site’s control, the climbing of Tower Crane 1 this coming weekend has been postponed. Permission has been granted by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 14th April 8am - 8pm Sunday 15th April … Continue reading Important Update: Change of date for extended working hours to increase height of tower crane

Important Update: Extended working hours to increase height of tower crane

We would like to take the opportunity to give you advance warning that the New Regent’s College project has been granted permission by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 7th April 8am - 8pm Sunday 8th April 9am - … Continue reading Important Update: Extended working hours to increase height of tower crane