Programme Update: November 2018

In October, the school has been preparing for its new ceilings to be installed. The Sports Hall has received its first coat of paint and the tower’s roof waterproofing works have been completed, as the remaining three levels of cladding are installed. Internal works on the floors below have continued, with some of the apartments … Continue reading Programme Update: November 2018

Programme Update: October 2017

Works during September 2017 During September, the site has completed the concrete to the basement slab and the basement’s columns. The ground floor slab construction has continued to enclose the basement areas. Drainage and the foundations for the new school have been completed, with the first area of the school’s ground floor slab concrete poured. … Continue reading Programme Update: October 2017

McLaren celebrate ground breaking at Nile Street development

McLaren and London Borough of Hackney celebrated the start of construction on site of the new Nile Street development in Hackney. The Mayor of Hackney, Philip Glanville and Ian Meredith, Director of Hackney Schools For The Future 2 Ltd officially broke ground on the site alongside The Head Teacher of New Regents College, Richard Brown … Continue reading McLaren celebrate ground breaking at Nile Street development